Thermal Power Russia:
Construction and Modernization of Plants
November 27-28, 2024, Moscow
November 27-28, 2024, Moscow
The International Forum and Exhibition Thermal Power Russia: construction and modernisation of stations is a professional international platform for leading companies in the Russian power industry involving senior executives of the largest investment projects, key generating plants in the region, regulatory authorities, investors, leading manufacturing companies, technology licensors , engineering, design and construction companies. The event is dedicated to the development of the thermal power industry through the realisation of major investment projects for the construction and modernisation of thermal power plants, as well as the exchange of experience and discussion of opportunities to improve the efficiency of existing production facilities.
Modernisation of the TPP-11 in Usolye-Sibirsky
Operator/Initiator: LLC Baikal Energy Company
Location: Irkutsk region, Russia
Stage: the development is underway
Dates: 2028
Investment Amount: 200 bn roubles
Boiler unit No. 3 is currently being upgraded at the station. The modernisation of the boiler is planned to be completed by 31 March 2025. It is also planned to build two new power units (boiler-turbine) with a capacity of 230 megawatts each at the TPP-11 industrial site. The activities are carried out according to the state programme of KOM NGO.
Thermal capacity – 1056 Gcal/hour, installed capacity – 320 MW; increase in capacity by 460 MW.
Modernisation of the Primorskaya state district power station
Operator/Initiator: Siberian Generating Company
Location: Primorye Territory, Russia
Stage: the development is underway
Dates: 2026
Investment Amount: 50.377 bn roubles
The Primorskaya state district station is the largest power plant in the Far East. It operates on the coals of the Luchegorsky coal mine. As part of the modernisation, it is planned to increase the output of the station to the equivalent of operation with an installed capacity for 6,500 hours per year. The installed capacity is 1,467 MW for electric and 237 Gcal/hour for thermal energy.
Modernisation of the Novosibirsk TPP-3
Operator/Initiator: Siberian Generating Company
Location: Novosibirsk region, Russia
Stage: –
Dates: 2024–2027
Investment Amount: 12 bn roubles
Siberian Generating Company is realising the reconstruction of one of the largest thermal power plants in Novosibirsk region – the TPP-3, which provides heat to almost the entire left-bank part of Novosibirsk. SGK will carry out the largest modernisation of the TPP-3 in recent decades. It is planned to replace 2 generators and 2 turbines, build a boiler, install 3 electric filters, which will ensure an increase in the power of the station and reduce the impact of the TPP on the environment.
Reconstruction of the Avtovskaya TPP (the TPP-15)
Operator/Initiator: TGK-1 (Gazprom Energoholding)
Location: Leningrad region, Russia
Stage: the stage of active modernisation
Dates: 2020–2025
Investment Amount: 15,8 bn roubles
TGK-1 is modernising the turbine units of the Avtovskaya TPP. The activities are carried out in three stages, the first of which began in 2020.
As part of the first stage, the modernisation of turbine units No. 7 and 6 and auxiliary equipment and general station systems will take place. The second stage will include the reconstruction of switchyard with a voltage of 35 kV and 110 kV and the construction of a circulating technical water supply system. The third stage will include the technical retrofit of the auxiliary equipment and systems of the station, including the reconstruction of four deaerators for feeding the heat network, steam pipelines with the installation of kindling boilers.
Construction of the Khabarovsk TPP-4
Operator/Initiator: PJSC RusHydro
Location: Khabarovsk Territory, Russia
Stage: the construction is underway
Dates: 2021–2025
Investment Amount: 57 bn roubles
To date, the capacities of the Khabarovsk TPP-1 are very worn out, so it is planned to build a new TPP-4 next to it, which will run entirely on natural gas, which will have a positive impact on the environment in Khabarovsk and on the amount of utility tariffs for heating, hot water and electricity. Diesel fuel will be used as a reserve at the TPP. The TPP-4 itself will consist of four GTU-TPP power units, each of which consists of one 82 MW gas turbine unit and one waste water boiler. In addition, it is planned to build a complex of cogeneration plants with five hot water boilers with a capacity of 180 Gcal/h each. The heat load of steam consumers will be covered from three steam boilers with a capacity of 30 t/h each. Electrical power – 328 MW, thermal power – 1368.3 Gcal/h/s.
Construction of the Ulan-Ude TPP-2 power unit
Operator/Initiator: TGK-14
Location: Republic of Buryatia, Russia
Stage: pre-design activities
Dates: 31 December 2028 – commissioning
Investment Amount: 26.3 bn roubles
A monitoring system will be installed on the chimney of the Ulan-Ude TPP-2, which will allow monitoring the concentration of harmful emissions in real time. the Ulan-Ude TPP-2 will also be equipped with a dry ash and slag removal system. It is planned to install the first oil-free ignition system in Russia. the TPP-2 will have the highest environmental and efficiency characteristics for the region. NOx emissions will be at the level of 350 mg, ash – 50 mg per normal cubic meter, which corresponds to the indicators of advanced foreign projects. The general designer was LLC KOTES Engineering. Up to 110 MW.
Deputy Minister
Ministry of Energy of the Kyrgyz Republic
President
Eurasian Energy Corporation
Head of International Relations and Investment Promotion Department
JSC Thermal Power Plants
Head of International Relations and Investment Promotion Department
JSC Thermal Power Plants
General Director
ACWA Power Sirdarya
General Director
Power Machines
First Deputy Director
RDI UzEngineering
Member оf The Board
Russian-Kyrgyz Development Fund
Chairman of the Board
Central Asian Electric Power Corporation JSC
First Deputy General Manager
KazNIPIEnergoprom Institute
Chief Strategy Officer
Aksa Energy
200+ participants – commercial and technical heads of investment projects, key generating plants in the region, regulatory authorities, investors, advanced equipment manufacturing companies, technology licensors, engineering, design and construction plants
Russian thermal power industry: the experience of the past, the challenges of the present, the strategies of the future
Looking into the future through the prism of innovation: technology trends for the thermal power market
Discussion of the development of 25+ projects in the thermal power industry. Tools for attracting investments
Economic and legal regulation in the thermal power and ensuring energy security of regions, tariff policy – discussion with representatives of regulatory authorities
The state of thermal power plants during the period of sanctions pressure. Maintenance of power equipment and technical retrofit of stations with available technologies, new supply routes
Improving the reliability and safety of thermal power plants and heat supply systems
20+ hours of business and informal networking! One-on-one meetings, business lunches, coffee breaks, cocktail reception, and much more.